14th Street Bridge Improvement Project

The Georgia Department of Transportation has released an updated project schedule for the replacement of the 14th Street Bridge. The new schedule will allow the department to reduce the amount of time that residents, employees, and visitors will be affected by construction activity.

Current Schedule

Starting next week (October 1), Williams Street between 10th Street and 16th Street will be reduced to one lane until June 2009. Motorists will be encouraged to bypass Williams Street at 10th Street by using West Peachtree Street.

In March 2008, Techwood Drive will be closed to traffic between 16th and 10th Streets. The roadway is expected to reopen by September 2009.

In fall 2008, the 14th Street Bridge will be closed to traffic and will not reopen until summer 2010. Motorists will be detoured to the 17th Street Bridge during this period.

Additionally, in March 2008, DOT crews will begin resurfacing the Downtown Connector between University Avenue and 10th Street. During construction, interstate lane closures will occur at night - Monday through Thursday from 7:00 p.m. until 6:00 a.m. - with continuous closures on weekends starting Friday night and concluding Monday morning.


On October 1st, Midtown Transportation Solutions will launch a web site, www.14thStreetBridge.com that will act as a resource center for commuters and employers. This site will provide information on lane closures, detour routes, commute alternatives, and solutions for employers.

Date: 2007-09-24 06:27 pm (UTC)
From: [identity profile] rick-day.livejournal.com
yeah I got this too. Does not affect us too much here at the Center.

Date: 2007-09-24 10:12 pm (UTC)
From: [identity profile] happyfunnorm.livejournal.com
Why are they replacing the bridge instead of fixing the 80 million potholes and steel plate sections of 14th?

Date: 2007-09-24 10:14 pm (UTC)
From: [identity profile] uglor.livejournal.com
They are widening 14th street, and will be redoing it from Spring Street across.

Date: 2007-09-25 04:59 am (UTC)
From: [identity profile] billings.livejournal.com
Maybe they will install a device that teleports cars into the sewer

Date: 2007-09-24 10:36 pm (UTC)
From: [identity profile] gargleoil.livejournal.com
2009???
gee, that's great...

Date: 2007-09-25 05:42 am (UTC)
From: [identity profile] notgruntled.livejournal.com
One of these days, they'll finish an Atlanta road project without starting the next one. I'm not optimistic that I will live to see it.

Seriously, wasn't it about half an hour go that they finished the last 14th St. bridge expansion? That is a corridor that's chasing I-285 for the World's Longest Permanent Road Construction Zone. Well, second-longest, after Boston's Big Dig, which had a start date around the age of Voltaire and is expected to be finished just before the sun goes nova. By the time they finish that thing, the last off-ramp will be at Milliways.

Date: 2007-09-25 05:44 am (UTC)
From: [identity profile] uglor.livejournal.com
The 14th street bridge has been pretty much the same since I moved downtown in 1992.

Date: 2007-09-25 11:03 pm (UTC)
From: [identity profile] notgruntled.livejournal.com
Oh, carp.I was thinking about the 17th st., part of the whole Atlantic Station carnival. 14th is one of the boring ones.

Or was.

July 2017

S M T W T F S
      1
2 345678
9101112131415
16171819202122
23242526272829
3031     

Style Credit

Expand Cut Tags

No cut tags
Page generated Oct. 5th, 2025 05:28 am
Powered by Dreamwidth Studios